A lot has happened at our school project over these past years. This update is meant to give you an overview of the project progress since the start of the project.

What has happened

Before 2016

  • land has been purchased

2016

  • school/campus farm running (cashew nuts, mangoes & vegetables)
  • soccer pitch ready
  • school administration office and store built
  • water well dug
  • built office toilets and septic tank
  • start of building first classroom till roofing level
  • brick making machine & brick making in progress

2017

  • school/campus farm running (cashew nuts, mangoes & vegetables)
  • first classroom is roofed, floored and doors/windows are fitted
  • 2 more classrooms built till roofing level
  • security house and store built
  • beefarming started
  • chicken coop built and keeping chickens
  • church and community centre built and in use

2018

  • finished and furnished 1st block of 3 classrooms
  • student toilets and septic tank built
  • kindergarten first class has started
  • build 2nd block of 3 classrooms
  • furnished staff office
  • build chicken-farm
  • put up a playground for the school

2019

  • kindergarten
  • built block 3 and roofing classroom blocks 2 and 3

2020

  • staff housing - 2 adjoining houses built
  • kitchen built and roofed

2021

  • 1st year of Former one started studies
  • adding doors and windows to block 2
  • finishing floors and walls in block 2
  • science lab furnished with tables
  • fencing around the school compound
  • final registration of the school

2022

  • 1st and 2nd class running

2023

  • 3rd class running
  • fit the water well with a pump and piping
  • equiping the science labs with needed equipment
  • started on the watchmen house

2024

  • 4th class running
  • finished off block 3 with doors, windows and painting
  • equiping the science labs with needed equipment
  • bought a car for transport
  • fencing around the school compound
  • finished another teachers house and the watchman house

 

What has been planned for

2025/26

  • building of the girls hostel
  • fencing around the school compound finalized
  • starting of vocational classes, such as tailoring

2027

  • Building of administration block