Project Progress Update 2022
Details:
Category: Kisarawe School Project
| Created: 05 February 2022
| Hits: 2428
A lot has happened at our school project over these past years. This news is meant to give you an overview of the project progress since the start of the project.
What has happened
Before 2016
- land has been purchased
2016
- school/campus farm running (cashew nuts, mangoes & vegetables)
- soccer pitch ready
- school administration office and store built
- water well dug
- built office toilets and septic tank
- start of building first classroom till roofing level
- brick making machine & brick making in progress
2017
- school/campus farm running (cashew nuts, mangoes & vegetables)
- first classroom is roofed, floored and doors/windows are fitted
- 2 more classrooms built till roofing level
- security house and store built
- beefarming started
- chicken coop built and keeping chickens
- church and community centre built and in use
2018
- finished and furnished 1st block of 3 classrooms
- student toilets and septic tank built
- kindergarten first class has started
- build 2nd block of 3 classrooms
- furnished staff office
- build chicken-farm
- put up a playground for the school
2019
- kindergarten
- built block 3 and roofing classroom blocks 2 and 3
2020
- staff housing - 2 adjoining houses built
- kitchen built and roofed
2021
- 1st year of Former one started studies
- adding doors and windows to block 2
- finishing floors and walls in block 2
- science lab furnished with tables
- fencing around the school compound
- final registration of the school
What has been planned for
2022
- 1st and 2nd class running
- solar energy for the whole school
- fit the water well with a pump and piping
- finishing off block 3 with doors, windows and painting
- fencing around the school compound finalized
- equiping the science labs with needed equipment
2023
- building of the girls hostel