Project Progress
What has happened
Before 2016
- land has been purchased
2016
- school/campus farm running (cashew nuts, mangoes & vegetables)
- soccer pitch ready
- school administration office and store built
- water well dug
- built office toilets and septic tank
- start of building first classroom till roofing level
- brick making machine & brick making in progress
2017
- school/campus farm running (cashew nuts, mangoes & vegetables)
- first classroom is roofed, floored and doors/windows are fitted
- 2 more classrooms built till roofing level
- security house and store built
- beefarming started
- chicken coop built and keeping chickens
- church and community centre built and in use
2018
- finished and furnished 1st block of 3 classrooms
- student toilets and septic tank built
- kindergarten first class has started
- build 2nd block of 3 classrooms
- furnished staff office
- build chicken-farm
- put up a playground for the school
2019
- kindergarten
- built block 3 and roofing classroom blocks 2 and 3
2020
- staff housing - 2 adjoining houses built
- kitchen built and roofed
2021
- 1st year of Former one started studies
- adding doors and windows to block 2
- finishing floors and walls in block 2
- science lab furnished with tables
- fencing around the school compound
- final registration of the school
What has been planned for
2022
- 1st and 2nd class running
- solar energy for the whole school
- fit the water well with a pump and piping
- finishing off block 3 with doors, windows and painting
- fencing around the school compound finalized
- equiping the science labs with needed equipment
2023
- building of the girls hostel